Lean construction
A design and construction administration process based on Japanese “lean manufacturing principles” which is designed to promote efficiency and eliminate waste.
Alternate Bid Proposal
A stated amount of money that is added or deleted from the base bid if the potential change in the project scope, materials or construction methods is accepted.
As-Built Drawings
Completed project documents showing all work changes as marked up by the General Contractor.
Bid Bonds
A legal document obtained by the contractor that provides security equal to the bid amount.
Bidding
Once construction drawings and specifications are completed and approved, interested contractors with the resources and experience to build the facility submit written estimates covering the total cost of labor, subcontractors, materials, expenses, overhead, and fee to construct the facility. Often, the contractor that submits the lowest bid is awarded the project provided the firm meets minimum qualifications.
Bonding Capacity
The maximum amount of credit coverage the surety will extend to the company.
Bond
Three-party agreement between the owner, the contractor and the bonding company.
Certificate of Occupancy BACK TO TOP
Issued to owner by the public building officials after their inspection is complete and the project is deemed to comply with the building, fire, and other applicable code provisions.
Change Order
1. The client’s written order to the contractor, which authorizes a change in the construction work and contract time and/or amount. Typically, the design professional also signs the change order and then issues it to the contractor.
2. Modifications to the contract documents after the project begins.
3. Written order to the contractor signed by the owner and engineer/architect, issued sometimes even after the execution of the contract, authorizing a change in the work or an adjustment in the contract sum or the contract time. A change order may be signed by the architect or engineer, provided they have written authority from the owner for such procedure and that a copy of such written authority is furnished to the contractor upon request. A change order may also be signed by the contractor if he agrees to the adjustment in the contract sum or the contract time. The contract sum and the contract time may be changed only by change order.
Commercial Construction
Includes the construction of such projects as office buildings, shopping centers, sports complexes, and hotels.
Commissioning
The procedure by which a completed building or manufacturing/industrial process is tested and certified to be in operable condition (the condition is rendered by the plan and design function).
Conceptual Design
The first phase of design, in which drawings are the dominant tool and product. Usually, drawings in this phase are composed of simple, single-line floor plans, building sections, elevations, and site plans.
Conceptual Estimating
A process of assigning cost parameters to a project during the earliest phase of project design, prior to establishment of a defined scope or plan.
Constructability Analysis
A process that studies project plans to determine how efficiently, effectively, and safety the plan can be built.
Construction Documents
The written and drawn materials which are the result of a design team’s efforts. They include working drawings, specifications, and other construction documents. They detail all information needed to construct the project and all legal requirements of the project.
Construction Manager At Risk
A sole proprietorship, partnership, corporation, or other legal entity that assumes the financial risk for construction, rehabilitation, alteration, or repair of a facility at a contracted price. The construction manager at risk serves as a general contractor and provides consultation to the client regarding construction during the design of the facility and also through construction.
Construction Management (CM) for Fee
1. A contractual arrangement in which an agent (construction manager) is hired to coordinate the total construction of a project. The basic objective is to integrate the project planning, design, and construction phases.
2. A project management delivery system that differs from the traditional design-bid-build system by utilizing the services of a construction manager who becomes a member of the team of owner-architect-construction manager. The manager’s role is to coordinate and communicate the entire project process utilizing his/her skill and knowledge of design and construction to clarify cost and time consequences of design decisions as well as their construction feasibility; and to manage the bidding, award, and construction phases of the project. The project owner’s objective in utilizing construction management is to minimize project time and cost while maintaining quality, function, and aesthetics.
3. A project delivery method whereby the client retains a construction manager to provide certain preconstruction expertise including cost estimating, value engineering, scheduling, and coordination of all activities during the construction phase of the project.
Design Development
The period following the schematic design stage, during which detailed scale drawings, specifications, and construction materials lists are produced. This includes detailing floor plans, elevations, and sections and producing drawings that show all building elements including staircases, windows, doors, structural plans, lighting, electrical outlets, electronics, plumbing, and mechanical systems.
Daily Construction Report
A written record of the days activities; weather conditions, work accomplished, number of personnel for each trade involved, equipment involved, materials received, visitors or inspectors present, and problems encountered.
Design-Bid-Build
Separate organizations with separate contracts with an owner wherein design plans and specs are first prepared by a licensed architect/engineer and then awarded through a competitive bid process to select a contractor to complete the construction. Proceeds in a linear or sequential fashion; design is completed before bidding, and bidding is completed before construction.
Design-Build
The entity contractually responsible for delivering project design and construction. The Design-Builder can assume several organizational structures, the four most common being a firm that possesses both design and construction resources in-house; a joint venture between designer and contractor; a contractor-led team with the designer in a subcontractor role; and a design-led team with the contractor in a subcontractor role.
Facilities Planning BACK TO TOP
The effort by which the overall needs and wants of the owner are documented. This documentation includes group and building and reflects spatial relation requirements and general layout.
Fast-Tracking
1. A method of construction management which involves a continuous design-construct operation. Construction work starts before final plans and specifications are complete. For example, excavation may start before superstructure plans and details are finished.
2. Sequencing construction activities so that some portions of the project enter construction before design is completed on other portions.
3. A method in which the design and construction phases overlap, with the construction of phase one beginning before the design of the next phase is complete.
Feasibility Studies
A detailed investigation and analysis of factors influencing the project to determine if the project is viable, such as type of structure, the location of the proposed project, the sources and availability of funding, and availability of utilities are examined and weighed against the financial return expected.
Finance Services
Services include financing and ownership structuring, capital budgeting, and conceptual cost estimating.
General Conditions of the Contract
Contains the governing articles that identify the parties of the contract and define the specific roles and responsibilities. General in scope and consist of standard articles that apply to most construction projects.
As opposed to general conditions of the project which are ancillary or supplemental services (temporary electrical, trash removal, etc.) which are required to do the job, but will not be a part of the job.
General Contractor
1. Responsible for the physical construction of the project.
2. The prime or main contractor.
General Liability Insurance
Protects the contract from claims resulting from the contractor’s construction operations that result in bodily injury or property damage to a third party.
Green Construction
An organized effort to design and build buildings using a process and materials which promote environmental sustainability.
Industrial Construction BACK TO TOP
Includes the construction of such projects (building and production/process lines) as manufacturing facilities, processing plants, power-generating plants, and factories.
Institutional Construction
Projects usually constructed for private or government entity, including schools, colleges, correctional facilities, and hospitals.
Lean Construction
A design and construction administration process based on Japanese “lean manufacturing principles” which is designed to promote efficiency and eliminate waste.
Master Planning
1. A plan, usually of a community or city, made to guide or restrict future development.
2. Master plans are developed for new and existing campuses for health systems, senior living communities, and universities which often includes market demographic analysis, volume projections, budgets, schedules, and site planning.
3. An overall scheme for phased work or construction. It combines forecasts of future activities, services and strategic planning with the organized development of physical facilities to meet staffing and space needs projections, typically for a period of 10 to 20 years.
Mechanical Installation
Installation of mechanical systems (i.e. HVAC) on the maching and process equipment in an industrial project.
Negotiate BACK TO TOP
Process to allow the owner and contractor the opportunity to come to an agreement about the project costs and contractual arrangements.
OSHA
Occupational Safety and Health Administration
Owner’s Representation
Complete Owner’s Representative services, from project concept through completion, are offered including acting as an owner’s single source of responsibility for all project related needs and leading the planning, design, and construction phases of the project.
Pre-Qualifications
Based on the contractor’s financial stability, experience, or any other qualifications the owner chooses to include.
Program Management
Delivering a project or projects from concept through completion using a team of experts whose sole focus is obtaining the owner’s goals. Program management combines the ability and resources to define, plan, implement, and integrate every aspect of the comprehensive program.
Programming
The early stages of a project, during which the architect and owner discuss the goals, needs, and function of the project; design expectations and available budget; and pertinent building code and zoning regulations. The architect then prepares a written statement setting forth design objectives, constraints, and criteria for the project, including special requirements and systems and site requirements.
Project Schedule
A schedule wherein activities are assigned a duration and sequenced in a logical order.
Punch list
1. A list of incomplete or unacceptable items, which ideally is compiled when the project is 99 percent complete. The contractor should perform its own punch list prior to the A/E review; however, it is the A/E’s list that generally is referred to as the punch list.
2. Record of deficiencies found during the inspection that must be corrected or completed before the project is accepted.
Quality-Assurance/Quality-Control (QA/QC) System BACK TO TOP
A documented system that specifies the procedures to be followed to measure and document the quality of the construction and certifies compliance.
Quality Management
The development, implementation, and administration of the quality-control system by the contractor.
Real Estate Services
Services range from site selection and analysis to assistance in acquisition all the way through to securing the necessary approvals.
Schematic Design
Scaled floor plans, building sections, elevations, and site plans. Schematic designs almost always include outline specifications indicating the types of engineering systems, glazing (glass), and doors and may include three-dimensional perspectives of the exterior as well as models of the entire building or portions of it.
Site Plan
Drawings that provide an overhead perspective on how buildings, parking areas, and other facilities would appear on a site. A site plan might also show service routes, landscaping, site zoning, sidewalks, expansion forecasts, neighboring streets, and other buildings.
Specifications
Detailed written descriptions of building systems, materials and fixtures to supplement and add specificity to the architects’ and/or engineers’ drawings.
Value Management
1. Substituting building types, systems, materials or finishes that reduce costs without compromising objectives and needs. The process exposes potentially hidden building costs that may not have been anticipated for the building’s operations.
2. The process in which the design is analyzed to reduce the project cost without sacrificing the needs of the owner.